History  Washington Hotel Lobbs Hole (kiandra) built early 1900's Australia's biggest hotel under one roof

Following the gold and copper mining ceasing it was moved to American Gold fields (later named Humula after the local cattle station ) 

They loaded the corrugated roof trusses ceilings doors windows and timber floors onto bullock carts and dragged it 130km from 4,200ft above sea level down hill to Humula 1000ft above sea level in the Snowy Valleys 50km from Tumbarumba

 

 

Robert and Gail take on the Humula Heritage Hotel Project Nov 2021 

A 3 year renovation and conversion to Guest House offering Dinner Bed and Breakfast in our home

We will breath life into a 110 year old building which was in ruins it was abandoned too hard basket.

It was left empty for 7 years rotting from water damage from overflowing gutters full of bugs nest dead animals

First job clean out 15 x 14 tons = 210 tons of rubbish junk tyres floors cupboards lounges mattresses fridges and hundreds of 1.5metre rotten stumps

Its not a job for the faint hearted its really a Labour of love.

My Motto Best way to eat an Elephant is one mouthful at a time.  

        

 

Image and Video Gallery click links to view.

Exterior

Extension non heritage

Heritage Roof to be painted 2023

Heritage Verandah to be extended 2023

Swallow Suite 

Ballroom Suite

Main Residence

Bakery Suite

        Outhouse Suite

Ensuites to be built 2023

Main Entry

Cellar

Dining

Kitchen

Courtyard

Carports & Parking 2023

Gardens Agg Drains Tanks Fences 2023 

February 5th Drive home to Humula

February 4th Isaacs Birthday Party

February 3rd Isaacs Day at Wangi

February 2nd Drive to Wangi Wangi

February 1st Water Gardens and Tidy up Yard plus talk to Phillip Engineer about the Floors

January 31st Spray weeds front back and Gardens

January 30th Build Door Frame and Window frame shed one

January 29th Lay Timber Floor for shed one

January 27th Sort out Timber Set up table top saw

January 26th Install Solar Panel in Bedroom

January 23rd Air Conditioner Installed

 

January 12th got home to weeds

January 1st to 11th  on cruise and nz holiday

December 24th Day in the Rain In Sydney

December 23rd taxi to Cruise ship

December 22nd stay at Rydges airport leave car

December 21st Xmas party at coffee club plus deliver xmas gifts 

go through facebook and photos

November

October

September

August

July

June

May

April

March

February

January

December

November

October

September

August

July

June

May

April

March

February

January

December 21st Cruise holiday

December 1st

November 1st

October 1st 

September 30th Goulburn

September 29th johns funeral Goulburn

September 28th roof unable to paint

September 27th Plumber Quote

September 26th Created Plans and diagrams

September 25th gravel Appt one

September 24th Dug Gravel Drains

September 23rd Painted Ceiling lounge

September 22nd shovelled gravel

September 21st Motel Construction Certificate

September 20th remove sink in bathroom cover bath fit table for kitchen

September 19th Motel office work 

September 18th removal truck arrives  

September 17th painting room1 bedroom move kitchen furniture clean bathroom

September 16th finish gravel room 1 and plaster room 2

September 15th blue metal room 1 and painting room 2

September 14th blue metal room 1 and painting room 2

September 13th blue metal and sanding

September 12th day off at peards bought windmill and farm stall

September 11th blue metal room 1 and painting room 2

September 10th blue metal room 1 and painting room 2

September 9th laid flooring and painted room 2

September 8th potted plants and mowed lawn pumped water

September 7th mowed lawn bought water pipe and wagga ct scan

September 6th Gail Mowed Grass fixed water pipe laid flooring

September 5th Telstra land line and repair water pipe

September 4th rest day at albury to get agg pipe

September 3rd removed base of water tank and dug drain

September 2nd more guttering and into wagga for owner builder and robs ultra sound

September 1st removed front guttering

August 31st checked drain with white paint

August 30th ian to hume dam and airport

August 29th Ian visits Humula 

August 28th drive to holbrook with ian

August 27th aaron nicole ian and isaac at voco

August 26th pick up ian and return to voco

August 25th Hair at Cessnock ians bithday

August 24th Gails Bday at Voco overnight

August 23rd Drive to Central Coast willows overnight

August 22nd Meet Engineer on site dig drain from fibro to the rear

August 21st dig hole in courtyard

August 20th Meet Don in Rain to Dig Agg Drains came home early

August 19th  Finish removing Courtyard Roof

August 18th  Courtyard Roof

August 17th start Courtyard Roof

August 16th remove stumps received chest nuts terry peel

August 15th Day off went to batlow podiatrist gail flu

August 14th fix floor over cellar

August 13th dug trench in garden and pumped out tea room

August 12th dug trench appt 5 front room and car port

August 11th dug trench appt 5

August 10th removed floor under desk

August 9th drove to beechworth saw waterfall gaol and church

August 8th removed floor cellar

August 7th pulled out stumps tea room

August 6th video of nest and birds

August 5th pumped out cellar

August 4th remove floor appt one

August 3rd remove floor appt one

August 2nd remove floor appt one

August 1st drove home

July 31st gail sick

July 30th gail sick

July 29th gail sick

July 28th met kun and drove nelson bay

July 27th Drove to Blue Mountains to see furniture

July 26th wagga dentist

July 25th drove back

July 24th Met John And Denise

July 23rd Met Marley at Chris

July 22nd Drive to Central Coast dinner Lake

July 21st remove add on

July 20th build new window appt 1 remove fibro

July 19th build new front door appt 1

July 18th wagga council and wagga tip

July 17th remove water tank

July 16th remove roof to courtyard

July 15th remove lean to car port

July 14th remove car port                        

July 13th paint loo and bathroom

July 12th wagga car service and drive to humula

July 11th day off

July 10th drive to albury nicole arrives

july 9th Ben Fusebox and get rid of freezers

July 8th andrew plumbing quote

July 7th roofer paint quote

July 6th roof gutters quote

July 5th move freezer to veranda

July 4th roof quote to paint 

July 3rd Quote for concrete Gail burning off Empty Water Tank

July 2nd Remove shelves and burn off, fix leaking pipe and get plumbing quote to remove roof and fix gutters

July 1st Strip Floors and shelves in Tea room 

June 30th Strip Floors in Tea Room find florin

June 29th Strip the fibro room burn off

June 28th Clean out the floors in the Tea Rooms move the reception desk 

June 27th Move the huge fridge assemble the scaffold 

June 23rd June 24th June 25th June 26th Central Coast family trip

June 22nd Chase up Scaffold and Concreters

June 21st A day in the office chasing up trades and resting more rain

June 20th A day changing locks sanding door frames and scraping loose paint

June 19th Filling the fourth 8 cubic metre skip with junk from tea rooms

A gold miners hand made tomahawk for digging dirt and setting traps

Horse shoes and axe heads plus lots of coins

June  18th Still cleaning up junk some great finds a box of 20 fluros and A pink baby suit.

I fell through floor 3 times expecting the bearers to be okay lucky its only 900mm deep

Our first Sunny day oh what a difference 17c instead of 3c

June 17th Pump out the cellar to find its concreted 4 m x 5 m with 6m ceilings with charlies help

concreted up to 1.9m deep just needs tiling and water heating pump

Today we use chain saw to remove a ton of wet floor boards and rotten bearers 

June 16th Day off from Cleaning so we go to Bunnings and shops Best buy work boots his and hers for $10 each

Plus Basketball hoop for $5

June 15th Today we get an electrician to check test and install safety switch

We lit two huge fires in the garden to burn timber junk 

June 14th Plumber fixes water heater burst pipe

We remove kitchen and find rotten floors

June 13th  We test chimney and light fire in apartment two

We find rotten floors in apartment one

Give away tyres and rims to locals

The Cellar has over 4 foot of water

Thats over 45cubic metres of water

I get a call from canada a new grandson 

June 12th We strip the bakery 4 rooms of junk

We remove a huge roller door 

June 11th We arrive to find the Ute was towed away

June 9th We fill 3rd 8 cubic metre Skip

We lay 8 sheets of flooring in apartment three

June 7th We fill 2nd Skip with junk in rain

The skip truck bogged in the driveway 

fukk day stripping Junk and building storage shed floors

June 5th Too wet for the 18 ton septic truck 

We filled the first 8 cubic metre skip

Its cold 3c at 9am snow at Tumbarumba

No Power No Heating No lighting

June 2nd The Clean up begins whilst commuting 60km each way

Empty the 19 rooms of all the junk left over from 100 years as a Post office,

General Store, Bakery, Haberdashery, Grocers, Mechanics and Service station.

Four huge truck loads of junk then we can see the floors........ 

June 1st We settle and begin the Humula project

 

View STEP BACK IN TIME RenovationProgress 

Location

9 MATE STREET, 2652, HUMULA

Phone: 0458091336
Mobile: 0458091336
Email: info@familclub.com.au

ABN:47 868 541 723

Mobile:  0458 091 336

Skype: RobertCWoodgate

Email: robert@familclub.com.au

Event Members:  21,819

LinkedIn:  8,292 Event Followers

LinkedIn for Events

Twitter:   familclub

Join Familclub here

Creating Business for the Event Industry

Familclub accepts Credit card, Paypal, Barter and Monthly Terms

100% Australian

australian-flag

advertise

From $100

Credit cards

familclub-accepts-paypal

LinkedIn

Search